J
Jaishree
Hi,
There is a project which has been budgeted and the project is subcontracted.
Based on the completion of tasks on time by the subcontractor specific
percentage of the total budgeted amount is awarded to the contractor. If the
time to complete the task is delayed a specific percentage is deducted from
the total budgeted cost.
Subcontractors send the update on the completion of the task and the date of
completion to an identified person who will be the assignment owner of the
tasks for the projects and feeds the data.
How should we plan a project for the above?
Should we have fixed cost for tasks, if so where can the actual cost for a
task be captured?
Please help.
Please help in creating a project plan.
There is a project which has been budgeted and the project is subcontracted.
Based on the completion of tasks on time by the subcontractor specific
percentage of the total budgeted amount is awarded to the contractor. If the
time to complete the task is delayed a specific percentage is deducted from
the total budgeted cost.
Subcontractors send the update on the completion of the task and the date of
completion to an identified person who will be the assignment owner of the
tasks for the projects and feeds the data.
How should we plan a project for the above?
Should we have fixed cost for tasks, if so where can the actual cost for a
task be captured?
Please help.
Please help in creating a project plan.