M
mcf_post
Hi there,
I'm developing an integrated workplan comprising several subplans. I wish
to tie them together through a milestone schedule at the top of the
integrated project that shows the key dependencies and drivers. A simplified
example: the HR plan and the IT plan are linked on:
HR gathers the data
IT cannot load the data until HR has gathered it
Once the HR data is loaded HR can start a payroll
I have 3 created milestones:
1. HR data gathered - dependent on a task in the HR plan
2. HR data loaded - a summary task in the IT plan, dependent on 1
3. Payroll initiated - Tasks in the HR plan, dependent on 2
This works great but I want to also reflect % complete. Is there a way to
show % complete on the milestone task at the top of the master plan?
Thanks...M
I'm developing an integrated workplan comprising several subplans. I wish
to tie them together through a milestone schedule at the top of the
integrated project that shows the key dependencies and drivers. A simplified
example: the HR plan and the IT plan are linked on:
HR gathers the data
IT cannot load the data until HR has gathered it
Once the HR data is loaded HR can start a payroll
I have 3 created milestones:
1. HR data gathered - dependent on a task in the HR plan
2. HR data loaded - a summary task in the IT plan, dependent on 1
3. Payroll initiated - Tasks in the HR plan, dependent on 2
This works great but I want to also reflect % complete. Is there a way to
show % complete on the milestone task at the top of the master plan?
Thanks...M