how to create primavera layout in ms project?

C

Colin

I believe there may be something similar -

Try inserting a few new columns (outline code 1-?)

These fields should act in the same way as activity codes in P3

Set up the fields in Tools/customise fields

Type in the relevant data per activity

Now set up grouping -
Project
Group by
Customise group by
Select the outline code fields
Format as required
OK

(This can also work for text fields - if you have already populated those)

Let me know if this is what you were after (and please rate)

Colin
 
A

azam

Thank you so much Colin ..this is what i am looking for & i never thought
that it is quite straight forward in MSP

regards,
azam
 
C

Colin

Azam

Thanks for the feedback.

I started off using P3, so I know how difficult it is to transfer to MSP.
Most things can be replicated. However, one thing that it can't do is a zero
float constraint. Also, in 2003 version(which I use) you cannot see the
driving task - This has been rectified in 2007.

Colin
 
L

larry

Colin,

I to came from P3, actually suretrak - understand they sold the
company...not quite sure whose selling the software anymore. Anyway, any
idea how you can control the display order of these groups?

Larry
 
C

Colin

Hi Larry

Sorry but I haven't checked my old posts for a while.

Oracle now owns Primavera

I'm sure I managed to do it like I did in P3 but can't remember

What I now do is put a value in front

eg

1) Engineering
2) Procurement
3) Factory
4) Site

Hope that helps

colin
 