Hi

I would like to create a base calender in MS project 2003. Can anybody
please guide me through the step by step process.

Thank you,
Chaitanya
 
D

Dale Howard [MVP]

Shiva --

Assuming you are using Project Server 2003 with Microsoft Project, and
assuming you are a Project Server administrator in your organization, do the
following:

1. Launch Project Professional 2003 and connect to Project Server with
administrator permissions.
2. Click Tools - Enterprise Options - Open Enterprise Global.
3. Click Tools - Change Working Time.
4. Click the New... button.
5. In the Create New Base Calendar dialog, enter a name for the Base
Calendar, select one of the two options, and click the OK button.
6. Set up the new Base Calendar according to your scheduling needs.
7. Click the OK button to close the Change Working Time dialog.
8. Save and close the Enterprise Global file.
9. Exit and relaunch Project Professional 2003.

If you are not a Project Server administrator, and are only a project
manager, then the default permissions in Project Server 2003 do not allow
you to create custom Base Calendars, as this permission is grated to Project
Server administrators only. Hope this helps.
 
S

Shiva Chaitanya

Hi Dale:

You are the best. I am really greatful to you for giving me the tremendous
solution.

Once again thank you very much.

Thank you,
Shiva Chaitanya.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top