H
Henrik
This is a design rather than technical question but I hope it still sparks
interest...
This is a bit tricky to explain so I'll describe the actual problem I'm
facing:
I'm developing a project plan for a product introduction in multiple
countries.
Some activities will be done centrally, consisting of several tasks which
can grouped together in workstreams, sub-workstreams etc -- for this, Project
and its task indent functionality works like a charm.
However, a number of activities will need to be done locally. For the sake
of simplicity, we can assume the activity set is identical across countries.
However, they will not be exectued at the same rate across countries. The
unit of analysis should clearly be the country, as eachcountry has specific
issues which influences progress and needs to be dealt with separately. There
are multiple countries (around 50) and activities (maybe 50 as well).
I'd like to avoid creating a long project plan which simply list all
activities for all countries, i.e. this structure:
Country 1
Activity 1
Activity 2
...
Activity 50
Country 2
Activity 1
Activity 2
...
Activity 50
....
Country 50
Activity 1
Activity 2
...
Activity 50
Is there a way to build in this multi-dimensionality in a smart way?
Thanks
Henrik
interest...
This is a bit tricky to explain so I'll describe the actual problem I'm
facing:
I'm developing a project plan for a product introduction in multiple
countries.
Some activities will be done centrally, consisting of several tasks which
can grouped together in workstreams, sub-workstreams etc -- for this, Project
and its task indent functionality works like a charm.
However, a number of activities will need to be done locally. For the sake
of simplicity, we can assume the activity set is identical across countries.
However, they will not be exectued at the same rate across countries. The
unit of analysis should clearly be the country, as eachcountry has specific
issues which influences progress and needs to be dealt with separately. There
are multiple countries (around 50) and activities (maybe 50 as well).
I'd like to avoid creating a long project plan which simply list all
activities for all countries, i.e. this structure:
Country 1
Activity 1
Activity 2
...
Activity 50
Country 2
Activity 1
Activity 2
...
Activity 50
....
Country 50
Activity 1
Activity 2
...
Activity 50
Is there a way to build in this multi-dimensionality in a smart way?
Thanks
Henrik