G
Greg
Try as I might I cannot seem to re-create the critical path of an already
completed project. I understand how the critical path is determined so it
makes sense that once all tasks are 100% complete there is no critical path.
I even tried saving a copy of the project file, changing all tasks to 0%
complete figuring that would do it, but no luck.
I'm running MS Project Pro 2002. Any ideas? We want to recreate the
original critical path for a lessons learned session. Thanks.
--Greg
completed project. I understand how the critical path is determined so it
makes sense that once all tasks are 100% complete there is no critical path.
I even tried saving a copy of the project file, changing all tasks to 0%
complete figuring that would do it, but no luck.
I'm running MS Project Pro 2002. Any ideas? We want to recreate the
original critical path for a lessons learned session. Thanks.
--Greg