How to differentiate the time usage between tasks for a resource

K

KT

This is an extension of the over allocation problem I had. I was able to
level the over allocated resource. Now say, I have two tasks, starting at the
same day assigned to a single recourse, 'Recourse A'. I want 'Recourse A' to
spend more time on Task B than Task A like he should spend 70% of his time
per day on Task B and the remaining 30% on Task A. If I set priorities, it
throws away less priority task at the end of high priority task (but I want
the resource to work on both simultaneously). Can somebody help? Thanks
 
J

Jan De Messemaeker

Hi KT,

There is no logic in Project that will dapt assignment units teh way you
want.
You can do that manually in the Task Usage or Resource usage view.
HTH
 