How to disable to enter actual hours for employees in PWA for pastdays?

S

speregud.trimedia

How to disable to enter actual hours for employees in PWA for past
days in MS Project 2003?

I want do not allow to enter actual hours for any tasks for past days.
So if an employee do not update his working time today, then he cannot
do it tomorrow for the previous day.

Maybe allow to enter actual hours for 2 or 3 past days.

How to do it?

Thank you
 
M

Mike Glen

Hi ,

Try posting on the microsoft.public.project.server newsgroup. Please see
FAQ Item: 24. Project Newsgroups. FAQs, companion products and other
useful Project information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 
C

Crook

Hello,

Mike is right, this is a project server question. May I suggest you
investigate use of managed time periods? Managed time periods may not be
exactly what you're looking for, but it should be close.

HTH,
Crook
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top