How to display all tasks happening in a day on the calender view?

D

Dominik

I'm using MS Project 2003. My problem is that I would like to inform people
in our plant what kind of activity will take place during the following weeks
on a day by day basis. I found the calender view and thought this would be
the ideal solution to my problem. Now, on the calender view there are only
few tasks displayed, but I would like to display all tasks that I have on my
gantt chart to take place that week.
Does anyone have a solution on where to customize the view in order to
display all tasks?
Thanks for any proposals!
 
J

Jan De Messemaeker

Hi,

Yes of course, simply drag and drop the bottom line of any week display to
show the necessary number of taks.
HTH
 
D

Dominik

Hi Jan,
my problem is that I have a lot of space on the page but project will only
put 3 or 4 out of 30 tasks on the page. I don't see, how that selection can
be influenced.
Cheers
 
M

Mike Glen

Hi Dominik,

Try Format/Layout/and check: Attempt to fit as many tasks as possible.


FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 