How to display data of a custom field in My Tasks

R

Robert

Hello,

I created an enterprise custom field (task entity) and then I entered some
data in this field in Project Pro 2007.
Whilst I published the project, the data of that custom field does not
display in the My Tasks page of PWA where I added the field.
What could be the problem?
Thanks
 
D

Dale Howard [MVP]

Robert --

Try the following:

1. Log into PWA with administrator permissions.
2. Click Server Settings - Enterprise Custom Field Definition.
3. Click the name of the custom field to open it for editing.
4. In the Calculation for Assignment Rows section, select the "Roll down,
unless manually specified" option.
5. Click the Save button.
6. Open a project and click File - Publish to publish it.

Does the data now appear in the field in the My Tasks page? Let us know.
 
R

Robert

Thanks a lot Dale : that works!

Dale Howard said:
Robert --

Try the following:

1. Log into PWA with administrator permissions.
2. Click Server Settings - Enterprise Custom Field Definition.
3. Click the name of the custom field to open it for editing.
4. In the Calculation for Assignment Rows section, select the "Roll down,
unless manually specified" option.
5. Click the Save button.
6. Open a project and click File - Publish to publish it.

Does the data now appear in the field in the My Tasks page? Let us know.
 