How to display hours as days

M

meg99

using 2003. I reveived a schedule that shows duration as hours. I
want to show the duration as days but I can't get the setting/options
to make it happen. What do I need to do?

meg99
 
J

JulieS

Hello Glen,

To convert duration to a measurement of your choice, choose Tools >
Macros, Macro select the Format_Duration macro and click the Run
button.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project