how to display work by resource for a summary task

V

vro

What's the easiest way to get the total hours, broken down by resource for a
particular summary task?
 
J

Jan De Messemaeker

Hi,

Resourced Usage View
Project menu
Group By, New Group
Click Group assignments, not resources
Group by Task Outline number (assignments)
Then By Name (resource)

That's it.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620