how to enter various hours

P

Parag Lawate

for task1 ranging from 1.1.09 to 30.4.09
i want to enter various hours on various days .(.not necessary 8 everyday)
is it possible? if so how?

thank u
 
P

Parag Lawate

i want to enter the following
for task1
start date is 1/1/09
end date is 30/4/09
total hrs is 50 hrs
but work different number of hours for different days
can i do so in msp?
 
V

vanita

Hi Parag

As Jan has suggested you may do this through VBA.

But, if not conversant with VBA, first you may assign a resource to the
activity through Gantt chart as work comes through resources. It would be
assigned equally on all days. Then change the task to fixed duration, remove
effort driven and in Task/Resource usage view make required changes in the
specific cells. A rudimentary method but works.

I hope it helps.
Vanita
 
S

Steve House [MVP]

The process is called Work Contouring and you can fine-tune the hours day by
day on either the Task Usage or Resource Usage views. Selecting the
particular assignment and opening the Assignment Information window will let
you also choose from several pre-defined contour patterns.
 