E
Elena Osipova
Hi,
could you please advise me on how to do such a thing:
- we develop a plan (WBS + task dependencies + durations)
- assign several tasks to one resource
- at each moment of time the system recalculates the % of workload for every
task assigned to have always 100% per day for each resource
Is it possible at all? Or may be the algorithm should work differently? The
main goal is to escape resource overload.
thanks,
Elena
could you please advise me on how to do such a thing:
- we develop a plan (WBS + task dependencies + durations)
- assign several tasks to one resource
- at each moment of time the system recalculates the % of workload for every
task assigned to have always 100% per day for each resource
Is it possible at all? Or may be the algorithm should work differently? The
main goal is to escape resource overload.
thanks,
Elena