How to export resource cost data to cvs w timephased cost increase

  • Thread starter Michelle Moulliet
  • Start date
M

Michelle Moulliet

All,

I have entered resource costs into my schedule, all in the same resource
table (A) with increases spread out every year, using the effective date
field in the resource cost table A. Is there any way to export and import
that data to and from Excel? I can't find these fields when I build my
import/export maps.

Thanks!
 
J

John

Michelle Moulliet said:
All,

I have entered resource costs into my schedule, all in the same resource
table (A) with increases spread out every year, using the effective date
field in the resource cost table A. Is there any way to export and import
that data to and from Excel? I can't find these fields when I build my
import/export maps.

Thanks!

Michelle,
Timescaled data is not exportable or importable via simple import/export
maps. Full import and export of timescale data requires VBA.

If you don't need to import that data, (i.e. export only), you could use
the "Analyze timescale data in Excel" utility found on the Analysis
toolbar of Project 2000 through 2003. If you have Project 2007, you can
export timescaled data via Visual Reports found under the Reports menu.

Hope this helps.
John
Project MVP
 