How to extract hours entered by my resources?

O

Ole Kristian Aas

Hi,

Being all new to Project Server, I need to find a way to extract timesheet
based on the information my resources have entered through PWA over the last
week/month/period. Ideally I'd like this filtered by projects.

Is there any way of doing this within the application itself, or do I need
to do queries myself?

If so, are there any ways of also extracting the comments made by the
resources as well in the same report?

Thanks.
 
G

Gary L. Chefetz [MVP]

Ole:

Try playing with the View Resource Assignments view that you can access from
the Resource Center. Does this get you close?
 
O

Ole Kristian Aas

It does ... this gives me a timesheet that will work. Brilliant.

Now, if I could get the comments as well ...
 