How to find a change on a resource change????

V

Vit

Hi to everybody,

I’m new on the vba on MS Project, before I have used it a lot on MS
Access…


I’m working on a Project Server Environment, and unfortunately, when
a
Project manager make change to some project, there is no opportunity
to highlight the changes…


I have tough to insert a custom field and assign it a specific value
if there is some changes on that task…


For example in on the task 1 a project manager changes the resources
of the usage of the resources, on the custom field I will find the
value “changed”..


Is possible to insert a vba code that automatically insert the value
“changed” if something change on the task???


I have find the following on the help : Private Sub
Project_Change(ByVal pj As MSProject.Project)
But unfortunately it works on the all project and not on the single
task…
Thank you so much to everybody


Cheers


Vit
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top