How to find out the actual for each day of a reporting period

V

Vivek S

Greetings,

We have not enabled 'Managed Time Period' option.

But I want to get a report in tabular format with DATES as columns and
Resource Names as rows and ACTUAL HOURS as data.
Basically it will give me what is the actual hours put in by each resource
for each day. I don't need to see against which task has the actual has been
put.

How can I create such a view in Project Server ?
 
E

elenoir

Hi,
I have to pull the similar report and the way I use is to go to "Resources"
and do "View resource assignments", you can specify a time period and the
outline level you want to see. Hope this helps.
Elvira
 
S

Steve Adams, PMP

Hi,

I have the same need. We used Portfolio Analyzer. Works great.

Ping me if you need help. Be glad to get you started.
 