How to find out the first task that is currently visible in MS Pro

P

Philsh

I am writing some vba code for Microsoft Project 2003 and I need to determine
which is the first task that is physically visible to the user on the display
in the ActiveProject. Is there a simple way to do this in vba (or some other
technique)?

Suppose I have 20 tasks that can all be visible. However, the user has
scrolled down so that task 4 is
currently the first task you can see on your screen. (The first three tasks
have scrolled off the screen.) Task 4 does not necessarily contain the
cursor. Is there a way to find that task 4 is the first task you can
currently see?
 
J

Jan De Messemaeker

Hi,

I sthis a coincidence or did you ask the same thing last week or so?
Project hasn't changed since, so sorry, no, not possible
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top