G
Girija
Hello ,
Sorry for resending this query, as I felt previous was not explained
properly.
I am using MSP 2003. Suppose there are 50 resources assigned to various
projects.
How do I know :
1) resource allocation of each resource i.e which resource is allocated to
which task in a project and
2) if there is overloading for a resource and when the resource is
overloaded / overallocated
Maybe you can call above points as, overall summary of a resource (which
gives the above informataion), Yearwise which can be drilled down like
quarter wise, from quarterwise to Monthwise , so on...
Requset you to update how the above information can be got through both, in
PWA and MSP.
Thanks in advance.
Girija
Sorry for resending this query, as I felt previous was not explained
properly.
I am using MSP 2003. Suppose there are 50 resources assigned to various
projects.
How do I know :
1) resource allocation of each resource i.e which resource is allocated to
which task in a project and
2) if there is overloading for a resource and when the resource is
overloaded / overallocated
Maybe you can call above points as, overall summary of a resource (which
gives the above informataion), Yearwise which can be drilled down like
quarter wise, from quarterwise to Monthwise , so on...
Requset you to update how the above information can be got through both, in
PWA and MSP.
Thanks in advance.
Girija