i have Actual work done and work remaining. Resources report the actual work
done and the work remaining to be done on each task enabled. And resrouces
reports their progress by % on task daily basis as they proceed through on
task.
this is interesting that resource complained that you schedule me for this
task for 2 hrs and i finished the task in 1 hr when i submit the progress i
have option to make % > 100% when i do that and click on recalculate it puts
2 hr below as task was for 2 hr. when i put 1 hr and recalculates it puts
50% in progress.
how can i tell my pm that 2 hr task was done in 1 hr & task was completed
100%.
Can some one help pelase.
i have Actual work done and work remaining. Resources report the actual work
done and the work remaining to be done on each task enabled. And resrouces
reports their progress by % on task daily basis as they proceed through on
task.
this is interesting that resource complained that you schedule me for this
task for 2 hrs and i finished the task in 1 hr when i submit the progress i
have option to make % > 100% when i do that and click on recalculate it puts
2 hr below as task was for 2 hr. when i put 1 hr and recalculates it puts
50% in progress.
how can i tell my pm that 2 hr task was done in 1 hr & task was completed
100%.
Can some one help pelase.