K
Kurt S
I have a project with a few long duration non-critical task which define the
ultimate duration of the entire project. However, I have a few critical
intermediate milestones which are critical. Does anyone know if there is a
way to force the critical path through specific milestones without date
constraining them?
Many Thanks.
ultimate duration of the entire project. However, I have a few critical
intermediate milestones which are critical. Does anyone know if there is a
way to force the critical path through specific milestones without date
constraining them?
Many Thanks.