R
raz1980
Hi,
I noticed in microsoft Project that when a taks is 100% complete, the
resource is still not available even when I re-level the resources.
For Example:
Resource IG has the following tasks
Task 1 4 days Tue 11/15/05 Fri 11/18/05 0% IG
Task 2 8 days Mon 11/21/05 Wed 11/30/05 0% IG Task 3 7 days Thu
12/01/05 Fri 12/09/05 0% IG
If IG finishes task 1 on time and then finishes task 2 early then he
should be able to start task 3, but the plan will not do that. If he
finishes task 2 on 11/23, then I would expect the plan (after
re-leveling) would should show that he starts task 3 on 11/24 and ends
on 11/31, but it does not change from the original.
Task 1 4 days Tue 11/15/05 Fri 11/18/05 100% IG
Task 2 8 days Mon 11/21/05 Wed 11/30/05 100% IG Task 3 7 days Thu
12/01/05 Fri 12/09/05 0% IG
The reason this bothers me is that it does not seem to show a realistic
view of whether the project is on schedule. For example, a resource
constraint was causing the end date of the project to be too far out,
but we made up the time, by finishing some tasks early. Now I want the
plan to reflect that the end date is on target. The only way I can
think to do it is to go in and change the original durations on the
tasks that are complete to reflect the time they actually took and not
the time originally scheduled, which would be a lot of work.
Is their an easier way, even if I have to use a formula?
Thanks
Bob
I noticed in microsoft Project that when a taks is 100% complete, the
resource is still not available even when I re-level the resources.
For Example:
Resource IG has the following tasks
Task 1 4 days Tue 11/15/05 Fri 11/18/05 0% IG
Task 2 8 days Mon 11/21/05 Wed 11/30/05 0% IG Task 3 7 days Thu
12/01/05 Fri 12/09/05 0% IG
If IG finishes task 1 on time and then finishes task 2 early then he
should be able to start task 3, but the plan will not do that. If he
finishes task 2 on 11/23, then I would expect the plan (after
re-leveling) would should show that he starts task 3 on 11/24 and ends
on 11/31, but it does not change from the original.
Task 1 4 days Tue 11/15/05 Fri 11/18/05 100% IG
Task 2 8 days Mon 11/21/05 Wed 11/30/05 100% IG Task 3 7 days Thu
12/01/05 Fri 12/09/05 0% IG
The reason this bothers me is that it does not seem to show a realistic
view of whether the project is on schedule. For example, a resource
constraint was causing the end date of the project to be too far out,
but we made up the time, by finishing some tasks early. Now I want the
plan to reflect that the end date is on target. The only way I can
think to do it is to go in and change the original durations on the
tasks that are complete to reflect the time they actually took and not
the time originally scheduled, which would be a lot of work.
Is their an easier way, even if I have to use a formula?
Thanks
Bob