I've got an administrative project I use to track non-billable, but
scheduled hours (vacations, conferences, etc.). After these events occur, I
mark them 100% complete, but I can't get them off the timesheets of my
resources...have you seen this...do you know how to get the nonproject time
off the timesheets?
The % Complete field is not editable by the resource...I entered hours in
the timesheet for the days these are scheduled, and submitted them, but they
will not come off even after approval.
Hide won't work...I get this error:
---------------------------
VBScript: Microsoft Office Project Web Access 2003
---------------------------
You cannot hide this task for one of the following reasons:
* It is a delegated task that you are a lead for
* It is a summary task with existing subtasks
* It is a nonproject time task defined by the server administrator
* It is a task transferred from Outlook
scheduled hours (vacations, conferences, etc.). After these events occur, I
mark them 100% complete, but I can't get them off the timesheets of my
resources...have you seen this...do you know how to get the nonproject time
off the timesheets?
The % Complete field is not editable by the resource...I entered hours in
the timesheet for the days these are scheduled, and submitted them, but they
will not come off even after approval.
Hide won't work...I get this error:
---------------------------
VBScript: Microsoft Office Project Web Access 2003
---------------------------
You cannot hide this task for one of the following reasons:
* It is a delegated task that you are a lead for
* It is a summary task with existing subtasks
* It is a nonproject time task defined by the server administrator
* It is a task transferred from Outlook