Z
ZH7
Hi,
I am new to MS Project and I am using MS Project 2003.
My situation is I have the project duration planned, for an example, from
Oct 10 to Oct 15. During that time, the actual working time will be one day
only and it has been completed.
I've been trying to set the percentage completed to 100% and then I cannot
set the day to one day. It changes to 5 days instead. Is there any way to set
the percentage completed to 100% while setting the actual working time to a
day (8 hrs)?
Thanks a lot for your time. Deeply appreciated.
I am new to MS Project and I am using MS Project 2003.
My situation is I have the project duration planned, for an example, from
Oct 10 to Oct 15. During that time, the actual working time will be one day
only and it has been completed.
I've been trying to set the percentage completed to 100% and then I cannot
set the day to one day. It changes to 5 days instead. Is there any way to set
the percentage completed to 100% while setting the actual working time to a
day (8 hrs)?
Thanks a lot for your time. Deeply appreciated.