How to get an end date for a schedule excluding Sundays?

T

Taner

I am making a schedule using Excel. I have the start date and the number of
days the employees will be working. I want to get the end date, but exclude
Sundays only. The employees work 6 days a week.

For example: Start Date: 4/1/2010
Number of working days: 7
The End Date would be: 4/8/2010

If I use WORKDAY it bases it off of Mon-Fri.
Not sure exactly the best way to go about this. Any help is greatly
appreciated!

Thanks
 
T

Taner

Hi,

I don't need to figure the workdays. I need to figure the end date from my
start date and number of days they will be working.
 
T

Taner

Ok I see how that works, but how do I get that to work in my work book? It
seems to work on your better workday workbook, but I don't know how to get
all of that function into my workbook.

Thanks
 