W
wixon21
Actually I have a process of 250 tasks, hopefully everything is linked
properly with proper calendars for the resources.
I am in the middle of a critical path analysis (after 55 steps of
generating new critical pathes). Until now it was possible to shorten the
lenght of the process with giving the command "as soon as possible" when
there was a gap between the tasks, or when I had an entire critical path with
start and end date, shortening the lenght of the acticity. The aim is to have
an earlier end date with a start date (deadline).
At the moment, the critical path is not continuous, the first few steps are
included among the critical activities, then there is a break. After the
break, until the end of the project, the rest of the activites are again
critical. I modified the length of those activities that were not among the
critical activities, that resulted in shortening the full length of the
process. It means that these steps should be included in the critical path
and they were not.
How is it possible to shorten one non critical acticity and making an
impact on the project? What should be done to have an entire continuous path?
I assume there is some problem with the calendars: if for one resource
there is a previously defined working time and all his time is not used
because he finishes the activity earlier, for making the path continuous it
was necessary to adjust the working time to the end of his activity. How is
it possible to find these problems easily?
properly with proper calendars for the resources.
I am in the middle of a critical path analysis (after 55 steps of
generating new critical pathes). Until now it was possible to shorten the
lenght of the process with giving the command "as soon as possible" when
there was a gap between the tasks, or when I had an entire critical path with
start and end date, shortening the lenght of the acticity. The aim is to have
an earlier end date with a start date (deadline).
At the moment, the critical path is not continuous, the first few steps are
included among the critical activities, then there is a break. After the
break, until the end of the project, the rest of the activites are again
critical. I modified the length of those activities that were not among the
critical activities, that resulted in shortening the full length of the
process. It means that these steps should be included in the critical path
and they were not.
How is it possible to shorten one non critical acticity and making an
impact on the project? What should be done to have an entire continuous path?
I assume there is some problem with the calendars: if for one resource
there is a previously defined working time and all his time is not used
because he finishes the activity earlier, for making the path continuous it
was necessary to adjust the working time to the end of his activity. How is
it possible to find these problems easily?