How to get % Planned Complete Calculation for FY

H

HCLIFF

I have a schedule the extends over two fiscal Years. As it currently sits
the % Planned Complete for the entire project is 60%. However, because the
new FY started in Oct. The % Planned Complete for the FY Should be 22%. Is
there a formula or a trigger to accomplish this?

Thanks
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top