Using PS07 and PWA.
Server setting =>TaskSetting=>Tracking Method =>[radio (on) "Hours of work
done per period. Resources report their hours worked on each task per period."
For projects ,we set task's based on MNhrs in MS07 . That is Task(A) = 18
Hrs or 35 Hrs etc etc and accordingly assign resources and level off.
Publish to server and PWA taks are visable to users.
PWA now show the task Duration as 2.25D or 4.37D on the task grid along with
the allocation hrs based on % unit as assigned to the resource across the
duration of the task.
When Users update their task, they still need to figure out how much time is
remaining for work item.
Users feel that if server displays the duration in Mnhrs it would be easier
to render feedback on estimated hrs remaing for work completion.
However, I can't figure out how to get server to display Duration in Mnhrs..
any suggestions.. yes duration is normally computed in Mandays..but manhrs
is a subset of mandays.. so why can't I configure that as my dispplay option
on PWA ? Is there any varable that I can tweak on server end or MS07 side to
get this done ?
/pd
Server setting =>TaskSetting=>Tracking Method =>[radio (on) "Hours of work
done per period. Resources report their hours worked on each task per period."
For projects ,we set task's based on MNhrs in MS07 . That is Task(A) = 18
Hrs or 35 Hrs etc etc and accordingly assign resources and level off.
Publish to server and PWA taks are visable to users.
PWA now show the task Duration as 2.25D or 4.37D on the task grid along with
the allocation hrs based on % unit as assigned to the resource across the
duration of the task.
When Users update their task, they still need to figure out how much time is
remaining for work item.
Users feel that if server displays the duration in Mnhrs it would be easier
to render feedback on estimated hrs remaing for work completion.
However, I can't figure out how to get server to display Duration in Mnhrs..
any suggestions.. yes duration is normally computed in Mandays..but manhrs
is a subset of mandays.. so why can't I configure that as my dispplay option
on PWA ? Is there any varable that I can tweak on server end or MS07 side to
get this done ?