V
Vivek Somani
Hi There,
I'm not sure if there exists a coined term for what I need. Lemme explain my
requirement in plain english.
"Most of my tasks are 'resource' specific and resources cannot be
interchanged. I have a project plan that runs into 500+ tasks.
When I add a new task, I provide 'Work' and 'Resource Name'. I would like
that the 'Start Date' be automatically calculated based on that particular
resource availability. Ideally it should be 1 day more than the last date on
which that resource is fully utilized. "
Any idea how to achieve this ?
PS : Manually looking for the specific resource's last date and then putting
that task ID as predecessor works but in a large project its too cumbersome
to search for the last date
Thks in advance,
Vivek
I'm not sure if there exists a coined term for what I need. Lemme explain my
requirement in plain english.
"Most of my tasks are 'resource' specific and resources cannot be
interchanged. I have a project plan that runs into 500+ tasks.
When I add a new task, I provide 'Work' and 'Resource Name'. I would like
that the 'Start Date' be automatically calculated based on that particular
resource availability. Ideally it should be 1 day more than the last date on
which that resource is fully utilized. "
Any idea how to achieve this ?
PS : Manually looking for the specific resource's last date and then putting
that task ID as predecessor works but in a large project its too cumbersome
to search for the last date
Thks in advance,
Vivek