I have scenario where i started overwhelming to fit tasks into my resources
schedule i.e. initially i had only 2 project so it was easy to fix tasks
schedules so that it does not overlaps task from other project...because we
do hour by hour planning.
Now i am planning to setup about 35 projects for same resource... and many
of this project has to run in parallel hence 2 hours 8am - 10am on 1 task
from one project, 3 hours 10am - 1pm on another task from another project on
same day etc...
i have hard time fingind any such view or report that tells me "during so
and so date the resource A is availabel for 4 hour between 1:00 pm to 4:00
pm."
i am using project professional 2007 with project server 2007 SP2.
if i get this report i can easily start filling our the gaps for new project
to fully utilize my resoruce.
can some one help to solve this please.
report should look like
Name Date Availability when
Mini feb-15-2010 2 hr 11am-1pm
james feb-15-2010 2hr 8am-10am
james feb-15-2010 3hr 2pm-5pm
I have scenario where i started overwhelming to fit tasks into my resources
schedule i.e. initially i had only 2 project so it was easy to fix tasks
schedules so that it does not overlaps task from other project...because we
do hour by hour planning.
Now i am planning to setup about 35 projects for same resource... and many
of this project has to run in parallel hence 2 hours 8am - 10am on 1 task
from one project, 3 hours 10am - 1pm on another task from another project on
same day etc...
i have hard time fingind any such view or report that tells me "during so
and so date the resource A is availabel for 4 hour between 1:00 pm to 4:00
pm."
i am using project professional 2007 with project server 2007 SP2.
if i get this report i can easily start filling our the gaps for new project
to fully utilize my resoruce.
can some one help to solve this please.
report should look like
Name Date Availability when
Mini feb-15-2010 2 hr 11am-1pm
james feb-15-2010 2hr 8am-10am
james feb-15-2010 3hr 2pm-5pm