How to get rid of pagination in My Tasks View (2007 server)

S

Stephan Steiner

Hi

We currently use Project Server 2003 and are looking at the 2007
server. I have set up one test server and imported all current
projects. I still need to get the hang of the difference between the
2003 timesheet and the 2007's My Task and My Timesheets but for now
I'm trying to enter time using the My Tasks view. There's but one
problem.. whereas all my assignments were visible on a single page in
the 2003 Time and in 2007 I have the whole thing split over 8
different pages.. which makes reporting time a major PITA (plus the
actual table only uses less than 50% of the available screen height
whereas I'd like to use all the available screen real estate).

Does anybody know how I can switch from a paged mode to a list
everything on one page and scroll vertically?

Regards
Stephan
 
B

Ben Howard

Hi Stephen

As an Administrator, on the my tasks page, click Site Actions | Edit Page,
edit the My Tasks Web Part (Modify Shared Web Part), Expand the Project Web
Access section and modify the items per page as necessary.
 
S

Stephan Steiner

Ben

I managed to increase the number of tasks that are being displayed so
I'm halfway there. However, the vertical size of the webppart is still
limited even though the webpart is set to use the maximum available
size...as it is now, I have the horizontal scrollbar on the same
vertical position as the "Server Settings".

Have you or anybody else managed to make the webpart fill the full
screeen?

Regards
Stephan
 