How to get tasks from different projects into a single plan

V

Vivek S

Hi,

Current Situation -- I have a product release and different teams work on
different feature of product. Each team has its own project plan and its
published on project server. The team members logs their time against project
plan to which they are attached.

As an overall responsibility, I have to create a view on Project Server web
interface that can report which tasks from each project plan will get
completed at a particular date. One option is to open each project and query
on Finish Date. But I have 20 project plans and doing this is cumbersome.

I want that on a single page, all the project plans appear with their task
details.

I read that Master Project Plan does not help (as it doesn't show the tasks
under subprojects which is what I really need !!).

Any other way to accomplish this??

Thanks
How to accomplish it ?

I want to know if
 
C

Chris Marriott

Vivek you are correct about the master plans ...

I have resolved this with a product called EPK

www.epkgroup.com

I have not found a workaround within Project Server itself to demonstrate
inner workings of the schedules from a portfolio view

I hope this helps
--
Regards


Chris Marriott - PMP MCSE MCDBA
UK - EPM Consultant & Trainer
 