How to get tasks scheduled for a particular day of a month

A

AppsProject

Hi,

I am trying to schedule task in this manner:

I have resources attending specific meetings on certain days of the month. I
want to capture the amount of time spent on the project for a given period of
time. Here are the details:

REsources: 2 in number
Meeting days: Alternate Wednesday of every month until December 2009 and
Weekly Thursdays until Dec 2009.
Duration: 1 hr for each meeting.

If I schedule by putting the resource on say 7% for the rest of the year, in
PWA it shows as 0.1 or 0.15 on that task every day for the resource. I do not
want it to be shown like that. I want to know if it is possible to show 1hr
for that Wednesday of that week the resource will be attending the meeting
rather than getting that 1 hr split across the 5 working days in PWA.

Is that possible? Hope I am making sense.

Please advice.

Thanks,
Aparna
 
M

mike

Hi,

I am trying to schedule task in this manner:

I have resources attending specific meetings on certain days of the month.. I
want to capture the amount of time spent on the project for a given period of
time. Here are the details:

REsources: 2 in number
Meeting days: Alternate Wednesday of every month until December 2009 and
Weekly Thursdays until Dec 2009.
Duration: 1 hr for each meeting.

If I schedule by putting the resource on say 7% for the rest of the year,in
PWA it shows as 0.1 or 0.15 on that task every day for the resource. I donot
want it to be shown like that. I want to know if it is possible to show 1hr
for that Wednesday of that week the resource will be attending the meeting
rather than getting that 1 hr split across the 5 working days in PWA.

Is that possible? Hope I am making sense.

Please advice.

Thanks,
Aparna

Have you tried scheduling the task as being recurring from within MS
Proejct Pro?

Insert, Recrrunt task, then choose your frequency.

Mike
 
A

AppsProject

Hi Mike,

Perfect! That helps. I never knew there was something called a recurring
task. Cool!

I have another follow-up question though:

I SHOULD have the resource name for each of the recurring task under the
main task, correct?

Thanks,
Aparna
 
M

mike

Hi Mike,

Perfect! That helps. I never knew there was something called a recurring
task. Cool!

I have another follow-up question though:

I SHOULD have the resource name for each of the recurring task under the
main task, correct?

Thanks,
Aparna








- Show quoted text -

You probably would wnat to use the granlar approach and assign each
resource to the specifiec meeting, rather than at the top summary
task.

Mike
 
A

AppsProject

Wonderful! That helps a lot. Thank you so much. And it works really good. :)

Aparna
 