A
AppsProject
Hi,
I am trying to schedule task in this manner:
I have resources attending specific meetings on certain days of the month. I
want to capture the amount of time spent on the project for a given period of
time. Here are the details:
REsources: 2 in number
Meeting days: Alternate Wednesday of every month until December 2009 and
Weekly Thursdays until Dec 2009.
Duration: 1 hr for each meeting.
If I schedule by putting the resource on say 7% for the rest of the year, in
PWA it shows as 0.1 or 0.15 on that task every day for the resource. I do not
want it to be shown like that. I want to know if it is possible to show 1hr
for that Wednesday of that week the resource will be attending the meeting
rather than getting that 1 hr split across the 5 working days in PWA.
Is that possible? Hope I am making sense.
Please advice.
Thanks,
Aparna
I am trying to schedule task in this manner:
I have resources attending specific meetings on certain days of the month. I
want to capture the amount of time spent on the project for a given period of
time. Here are the details:
REsources: 2 in number
Meeting days: Alternate Wednesday of every month until December 2009 and
Weekly Thursdays until Dec 2009.
Duration: 1 hr for each meeting.
If I schedule by putting the resource on say 7% for the rest of the year, in
PWA it shows as 0.1 or 0.15 on that task every day for the resource. I do not
want it to be shown like that. I want to know if it is possible to show 1hr
for that Wednesday of that week the resource will be attending the meeting
rather than getting that 1 hr split across the 5 working days in PWA.
Is that possible? Hope I am making sense.
Please advice.
Thanks,
Aparna