Hi
I have a Task which I know will take 80h and I have assigened a resource 50%
units. When tha task in 50% complete I need to change the units to 25%. When
I do this change Ms Project update the project accordingly, but I loose the
information that I got 50% units during the first half of the task.
How are you supposed to work with Ms Project if you want to keep track of
the Unit changes during the lifetime of a task?
Regards
/Niklas