Hi Ben,
Ok… Here is what I’m doing in a bit more detail…
Launch the Change Working Time dialog.
Use the Create New Calendar button to create a copy of the Standard calendar
called Day Shift.
Select the Work Weeks tab and click the Details button.
Select all days, select Set Days to these specific working times, enter the
correct work times for my shift, and click OK.
Select June 25, 2007 on the calendar.
Switch to the Exceptions tab, enter a label in the Name field and click the
Details button.
In the details dialog select Nonworking, Weekly and set the Recur every
counter to 4 weeks. Check the Monday and Tuesday boxes, then select End
After and specify 13 occurrences. Click the OK button to close the dialog
box.
At this point life is good! We have created the first two day break in our
28 day schedule and it reoccurs for the next year.
Now select July 2, 2007, enter a label in the name tab, open the Details
dialog and select exactly the same options. When you click the OK button you
will receive a Microsoft Office Project error dialog with the following
message:
The exception conflicts with #1 “xxxâ€.
They both use the same type of exception, Weekly, and their interval
overlaps. Either change the date range or change the type of exception.
The “xxx†displayed is the label I placed in the Name field of the first
exception.
I suspect this is a bug…
It would help me a great deal if you or someone could run through this same
process and verify the same result. Or, tell me what I’m missing.
The way it stands now, I can only get one exception to reoccur. This
implies that I would have to manually enter each day off as a separate
exception line. That works out to at least 104 manually entered exception
lines per year times at least 6 shift calendars. Ugly, ugly ugly…
Bob