K
KarthikK
Hi,
I have a project schedule. I would like to take the data from the Gantt
chart view. I am aware that Gantt Chart show's the way how the data is
distrubuted but i would like to get the total horus for a task for each
month. Would this be possible to do it in VBA?
Ex: I have a task like the one below
Prepare for Paper Presentation 80 dys? Mon 1/1/07 Fri 4/20/07 237 hrs
Plan the topic 8.88 dys? Mon 1/1/07 Thu 1/11/07 10 hrs
Start the Preperation 26.88 dys? Wed 1/10/07 Thu 2/15/07 180 hrs
Plan for Review 10 dys? Fri 3/2/07 Thu 3/15/07 15 hrs
Plan for Rework 10 dys? Tue 3/27/07 Mon 4/9/07 30 hrs
Present the paper 1 dy? Fri 4/20/07 Fri 4/20/07 2 hrs
The distribution in the GanttChart(Resource usage) would be something like
this
Prepare for Paper Presentation Jan: 116.33h Feb: 73.67h March: 27h April:20h
I assume these are the sum of the distribution of the child tasks under
"Prepare for Paper Presentation"
Is it possible to get the values using the (VBA Macro) for each month like
the above example?
Please let me know if you have any suggestions
Thanks
Karthik K
I have a project schedule. I would like to take the data from the Gantt
chart view. I am aware that Gantt Chart show's the way how the data is
distrubuted but i would like to get the total horus for a task for each
month. Would this be possible to do it in VBA?
Ex: I have a task like the one below
Prepare for Paper Presentation 80 dys? Mon 1/1/07 Fri 4/20/07 237 hrs
Plan the topic 8.88 dys? Mon 1/1/07 Thu 1/11/07 10 hrs
Start the Preperation 26.88 dys? Wed 1/10/07 Thu 2/15/07 180 hrs
Plan for Review 10 dys? Fri 3/2/07 Thu 3/15/07 15 hrs
Plan for Rework 10 dys? Tue 3/27/07 Mon 4/9/07 30 hrs
Present the paper 1 dy? Fri 4/20/07 Fri 4/20/07 2 hrs
The distribution in the GanttChart(Resource usage) would be something like
this
Prepare for Paper Presentation Jan: 116.33h Feb: 73.67h March: 27h April:20h
I assume these are the sum of the distribution of the child tasks under
"Prepare for Paper Presentation"
Is it possible to get the values using the (VBA Macro) for each month like
the above example?
Please let me know if you have any suggestions
Thanks
Karthik K