S
Stuart
Hi,
I have links in my schedule to other tasks that are in
other files. (project 2002)
When I run a cost report I notice that the costs of
external linked tasks are not included.
Is there a way to do this so I can get a report showing
the total cost?
Thanks,
Stuart.
I have links in my schedule to other tasks that are in
other files. (project 2002)
When I run a cost report I notice that the costs of
external linked tasks are not included.
Is there a way to do this so I can get a report showing
the total cost?
Thanks,
Stuart.