How to include the start and end date in the duration

K

kamran

Hi
When I enter my start and end date (e.g. 4/1/10 to 4/5/10) the project
calculates 3 days, I like it to calculate 5 day, which means including the
start and end date in duration. How can I set this up. Please help....

Thank you
 
A

Andrew Lavinsky

Typically, the system DOES include the Start and End date in the system.
In your example 4/1 - 4/5, that is three days: Thursday, Friday and Monday.
Do you wish to override the weekends? If so, simply create a new 7 day
calendar in Tools > Change Working Time and apply to the project and/or resources.

Then make sure the settings in Tools > Options > Calendar map to your new
settings.

- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm
 
K

kamran

Thank you for the information. I still have a problem setting the newly
created 7-working day calender as a default for my project. My tasks do not
recognize this new setting. My task timeline keeps going back to the
standard calender.

Thank you
 
S

Steve House

Once you have created the calendar, go to the Project menu, Project
Information, and designate it as the Project Calendar. The Timeline
display, though will still show the non-working days from the Standard
calendar untill you also right-click in the timeline, chose "timescale," the
non-working time tab, and switch from the Standard calendar to your new
7-day calendar.

Remember though, a 7-day calendar implies that when work starts on a task,
it proceeds every day without interruption. Don't your resources get a day
off? When you assign Joe to work on a task with a 2 week duration, does the
poor fellow really have to work every day until the task is done?
--
Steve House
MS Project Trainer & Consultant
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top