P
Pali
We know about baselining and once I baseline, I can compare variances.
However, if I have added additional resource during the execution of the
project to get some work done, is there a way to check later that this
project was completed with an additional resource?
One way could be to check for Work Variance and Cost Variance, but there
could be Work and Cost variance for various other reasons also.
I specifically want to know if I can get 'resource variance'!!
However, if I have added additional resource during the execution of the
project to get some work done, is there a way to check later that this
project was completed with an additional resource?
One way could be to check for Work Variance and Cost Variance, but there
could be Work and Cost variance for various other reasons also.
I specifically want to know if I can get 'resource variance'!!