How to limit the availabibility of an ent resource to a project

B

_Bob

I'm new to Projec and Project Server 2007 but can already see how useful the
two can be for us. Is there a way I can limit the availability of an
enterprise resource to a particular project? E.g. the resource has Max.
Unit of 100% but I just want to allocate 30% max to a particularly project.
I suppose it should be doable on the "Build Team From Enterprise" dialog box
but I can't figure out how. Thanks in addition for any suggestions.
 
M

Mike Glen

Hi Bob,

Try posting on the server newsgroup as this one is closing down. Please see
FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful
Project information can be seen at this web
address:http://project.mvps.org/faqs.htm .

Mike Glen
Project MVP
 