how to list all customers under one project name, with specific ta

W

wendy

Hello,
Was wondering how do I list all customers in Microsoft Project 2003, with
specific tasks under each customer, without having to Create a New Project
for each customer?

My problem I have now, (I was hoping Project would help me solve this
problem too), is I have over 20 clients that all pay me each month (contracts
are for 1 full year), for misc. tasks to be completed throughout each month.
I am struggling with how to manage where along the way each customer is at,
and which task I am supposed to complete for each client at any given time.
Where 1 customer is at is not where another customer is at currently.
Understand?

I would like to pull up a Project Report detailing a list of all customers
and which tasks have been completed for each client, and where each customer
is at during their year timeline contract.
 
S

Steve House

There's really no way to do that, as Rod has pointed out. You have AT LEAST
20 separate projects in the scenario you pose, perhaps many more than that.
A "project" is a time-limited set of activities resulting in the creation of
a SINGLE, UNIQUE, product, service, or result. Since I doubt that the
activities you do for 20 independent clients all come together at some point
into a single final result after which you do no more work for any of them
on anything, your collective work for the year isn't a project in the
project management sense at all.
 