C
chriswork
Hi all,
In 2003 the was the possibility of going into resources and selecting
adjust actuals, selecting all resources and how much time had been
input was available. If no work had been input the system would return
0, this could then be exported to excel.
However I am trying to track non submission in 2007 and I am
struggling. It appears that adjust actuals view has gone, which if you
are aware of where this has gone and how I can adjust the actuals for
a selected group of people that would be great. I have read a post
that discribed how to adjust actuals one by one, but in 2003 this
could be done on a select max 100 people level.
However the main point that I would like assistance with is the
checking the PWA for the users who have not submitted time as this
option is no longer visible. As discribed in the opening paragraph?
Thanks in advance,
Christopher
In 2003 the was the possibility of going into resources and selecting
adjust actuals, selecting all resources and how much time had been
input was available. If no work had been input the system would return
0, this could then be exported to excel.
However I am trying to track non submission in 2007 and I am
struggling. It appears that adjust actuals view has gone, which if you
are aware of where this has gone and how I can adjust the actuals for
a selected group of people that would be great. I have read a post
that discribed how to adjust actuals one by one, but in 2003 this
could be done on a select max 100 people level.
However the main point that I would like assistance with is the
checking the PWA for the users who have not submitted time as this
option is no longer visible. As discribed in the opening paragraph?
Thanks in advance,
Christopher