S
Seann
I'm trying to lock my resources into 6.5 hours of planned work per day so
that when I level the project, it schedule everyone at no more than 6.5 hrs.
I have tried to doing this by setting the max assignment units on every taks
to 81%, however that sets everyone's work day to 6.48hrs which is ugly.
6.5hrs is actually .8125%, however project does not go to decimals for units.
Is there another way to do this? I've dug through "change working time" but
nothing seems to work.
Any help is appreciated.
that when I level the project, it schedule everyone at no more than 6.5 hrs.
I have tried to doing this by setting the max assignment units on every taks
to 81%, however that sets everyone's work day to 6.48hrs which is ugly.
6.5hrs is actually .8125%, however project does not go to decimals for units.
Is there another way to do this? I've dug through "change working time" but
nothing seems to work.
Any help is appreciated.