S
spatton
I attended a training on MS Project 2003, in which the instructor
showed us how to create a true Project, and everything else was then
tasks of this project - as opposed to how we do it now, which is to
create a top level task which we call the "Project", then everything
else is a subtask of this. As we use Project 2007, the directions he
gave did not work for us. How in Project 2007 does one create a true
"Project", instead of just a top level task, followed by subtasks?
During the training for MS Project 2003, it was shown by going to
File>Properties.
If this all sounds confusing, as difficult to explain here, I can add
further detials.
Thanks
Steve
showed us how to create a true Project, and everything else was then
tasks of this project - as opposed to how we do it now, which is to
create a top level task which we call the "Project", then everything
else is a subtask of this. As we use Project 2007, the directions he
gave did not work for us. How in Project 2007 does one create a true
"Project", instead of just a top level task, followed by subtasks?
During the training for MS Project 2003, it was shown by going to
File>Properties.
If this all sounds confusing, as difficult to explain here, I can add
further detials.
Thanks
Steve