How to make a task to continue untill the end of the project?

N

Neury

I need to creat a Manager Task that will keep alive from the
start until the end of the project.

I can creat it, but if I change any date or durating of any other
tasks (increasing the duration, for exemple), the manager task
continue during the initial quantite of time. There is something that
I can do to link the end date of a task (in this case the manager
task) with other task?

For exemple, in Excel I would use: "MT = ED" where MT is the date of
the Manager Task and ED is the End Date of the linked task.

Thank you all.
 
M

Mike Glen

Hi Neury,

Welcome to this Microsoft Project newsgroup :)

Please see FAQ Item: 19. Hammock Tasks.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
 