Stefan van Aalst
For each project open I can see Actual Work done on those projects. If I
have only one project open I can see the amount of Work for each resource per
project (even when closed). What I need is to see in MS-Project all the
Actual Work (on project level) per resource without opening all the relevant
projects.
Is this possible? If so how to do this?
Strangely, I see that Overallocation (seems to) contain the numbers I'm
looking for.
In case there is a need to know why, I want to create an report per resource
what the hours they worked on what project per day/week/month. Ideally I
would like to use the cubes, but 'they' decided not to turn on the cubes for
the time being :-(.
Much obliged
Stefan
have only one project open I can see the amount of Work for each resource per
project (even when closed). What I need is to see in MS-Project all the
Actual Work (on project level) per resource without opening all the relevant
projects.
Is this possible? If so how to do this?
Strangely, I see that Overallocation (seems to) contain the numbers I'm
looking for.
In case there is a need to know why, I want to create an report per resource
what the hours they worked on what project per day/week/month. Ideally I
would like to use the cubes, but 'they' decided not to turn on the cubes for
the time being :-(.
Much obliged
Stefan