Bill Cole
When resources apply hours towards assigned tasks and the manager accepts
those hours, the "Finish" dates only update for tasks that the user had
applied hours toward, and tasks 'further down the schedule' which are
dependent on tasks that changed.
How can I tell Project to update the Finish dates of all tasks as of now to
reflect today's date and remaining work?
For example, the user has 10 tasks in his schedule, and is working on
various tasks at once. For this week he applied hours to tasks 3, 4, 5, and
8. So those tasks' Finish dates updated based on the Remaining Work and the
date the user entered hours for. And tasks that are dependent on these
tasks (which would be tasks 6, 7, 9, 10) update also.
HOW do I get tasks 1 and 2 to update? The resource didn't apply hours
towards these so Project didn't update them. Technically all 10 tasks'
Finish dates are wrong because
all depend on tasks 1 and 2, who's dates did not update and in fact may be a
date PRIOR to today.
- Bill
those hours, the "Finish" dates only update for tasks that the user had
applied hours toward, and tasks 'further down the schedule' which are
dependent on tasks that changed.
How can I tell Project to update the Finish dates of all tasks as of now to
reflect today's date and remaining work?
For example, the user has 10 tasks in his schedule, and is working on
various tasks at once. For this week he applied hours to tasks 3, 4, 5, and
8. So those tasks' Finish dates updated based on the Remaining Work and the
date the user entered hours for. And tasks that are dependent on these
tasks (which would be tasks 6, 7, 9, 10) update also.
HOW do I get tasks 1 and 2 to update? The resource didn't apply hours
towards these so Project didn't update them. Technically all 10 tasks'
Finish dates are wrong because
all depend on tasks 1 and 2, who's dates did not update and in fact may be a
date PRIOR to today.
- Bill