J
jas
All
How to make MS project record the date a task completes (Actual Finish
Date).
For example I have the following situation
As of Aug 5th
TASK A with a finish date of Aug 5th is 0% complete
Task does not start due to some a predecessor not completing in time
As of Aug 10th
TASK A with a finish date of Aug 5th is 100% complete. I want to make
sure that the "actual finish" date is reflected as Aug 10th.
Is it possible to track these task completion dates in project. Please
advise.
regards
How to make MS project record the date a task completes (Actual Finish
Date).
For example I have the following situation
As of Aug 5th
TASK A with a finish date of Aug 5th is 0% complete
Task does not start due to some a predecessor not completing in time
As of Aug 10th
TASK A with a finish date of Aug 5th is 100% complete. I want to make
sure that the "actual finish" date is reflected as Aug 10th.
Is it possible to track these task completion dates in project. Please
advise.
regards