J
Jef
Hello all,
I'm managing a project in which most of tasks are performed by a
partner at fixed cost. The problem is that I have term of payment such
as x% at order y% at delivery z% after final validation. I cannot find
a smart way to manage this. Fixed cost can only be assigned at
accrural start or end. I therefore made subtasks to the work as
milestones corresponding to payment steps (order, delivery,
validation) although I don't really like this approach which does not
allow to manage properly the % complete. Anyway I cannot store
somewhere the cost of the whole task and get automatic calculation of
the cost in subtasks,ie if whole task price is P cost assigned to
"order" subtask should be x% of P. I must calulate and enter it
manually.
I used custom cost fields to store at main task level cost1=ref price,
cost2=x% of ref, cost3=y% of ref and so on. I then linked-copied cost2
of main task in the fixed cost field of "order" sub-task and so on...
complicated and not smart is it ?
Beside I have standard resource follow-up but this is OK.
Did I miss something in MS-Project or am I mistaking wanting to
track all the project costs ? Actually I don't feel like making
duplicate work in Excel it will be a nightmare to keep both aligned
....
Thank you for your feedbacks
JF
I'm managing a project in which most of tasks are performed by a
partner at fixed cost. The problem is that I have term of payment such
as x% at order y% at delivery z% after final validation. I cannot find
a smart way to manage this. Fixed cost can only be assigned at
accrural start or end. I therefore made subtasks to the work as
milestones corresponding to payment steps (order, delivery,
validation) although I don't really like this approach which does not
allow to manage properly the % complete. Anyway I cannot store
somewhere the cost of the whole task and get automatic calculation of
the cost in subtasks,ie if whole task price is P cost assigned to
"order" subtask should be x% of P. I must calulate and enter it
manually.
I used custom cost fields to store at main task level cost1=ref price,
cost2=x% of ref, cost3=y% of ref and so on. I then linked-copied cost2
of main task in the fixed cost field of "order" sub-task and so on...
complicated and not smart is it ?
Beside I have standard resource follow-up but this is OK.
Did I miss something in MS-Project or am I mistaking wanting to
track all the project costs ? Actually I don't feel like making
duplicate work in Excel it will be a nightmare to keep both aligned
....
Thank you for your feedbacks
JF